I spent eight years building wind farms in Spain, the Netherlands and Germany. The wind farms went up, the energy flowed, and people in the next village kept paying the same electricity bill. Many didn't even know who owned the thing.

On 17 November, at the Diálogos Eólicos (Wind Dialogues), Spain's Secretary of State for Energy, Joan Groizard, announced a measure that could change that.

What was announced

The Government will put a ministerial order out to public consultation to regulate tenders for grid access capacity at transmission grid nodes, for wind only, with or without storage. Priority will go to projects that:

Groizard summed it up like this, according to El Periódico de la Energía: the winner will be “the best project, not the one that gets there first”. Nor the one that pays most in the tender.

The tool isn't new. Royal Decree 1183/2020 already allows tenders at nodes with available capacity. What's new is an order designed only for wind, with the local area built into the criteria.

There's no text yet. We don't know how much each criterion will weigh, which nodes will be included or when the tender will be called. First the order has to go out to consultation. Then comes the tender.

Why it matters

Grid access has mostly been handed out first come, first served. Whoever applied first got connected. That rewards whoever moves paperwork fastest, not whoever designs the best project for its surroundings. I pointed this out at the start of the series “The grid”.

A tender that scores what stays in the local area changes the incentive. The village stops being a formality and becomes part of the score.

Groizard listed four priorities: focusing on renewable acceleration areas, better permitting, keeping part of the profits in the area through “territorial excellence labels”, and repowering.

Reinvesting is not the same as taking part

This is where I have a doubt. “Reinvesting in the municipalities” can be met in many ways. An agreement with the council to fix a road. A fund for the sports centre. Or local people who own part of the wind farm and have a say alongside the developer.

It all adds up. But it doesn't build the same acceptance, and it doesn't leave the same thing behind once the agreement ends.

I covered this with the Dutch case: they put a 50% local ownership target in writing, and seven years later onshore wind stands at 44%. It worked because they measured ownership, not just compensation.

If the order defines clearly what counts as a local benefit, Spain can take that step. If it leaves it open, every developer will bring its cheque and the tender will go to whoever tells the best story.

Repowering is the other half

Groizard noted that the oldest wind farms have the best wind and the most social acceptance. And there's a queue to renew them: in July, Spain's energy agency IDAE awarded grants to 81 wind repowering projects, totalling 2,433 MW and €551 million. The Government is also finalising a royal decree so these wind farms can increase their capacity.

Many of these wind farms were built more than twenty years ago without asking the village. Repowering is the chance to rebuild that relationship: offer local people a stake and, where distance allows, bring part of the energy to their homes and businesses through collective self-consumption.

What I'd do now as a council

There's no need to wait for the order to get ready.

  1. Find out which wind farms exist or are in the pipeline in the municipality, and which node they connect to.
  2. Start talking to the developer before they turn up with the agreement already drafted.
  3. Ask for a stake, not just compensation: part of the ownership for residents, businesses or a local energy community.
  4. Organise local people. An established energy community is someone to negotiate with. A scattered village isn't.

To developers: the local package can't be improvised in the few weeks a tender lasts. It's built over time, with people from the area. At Sapiens Energía we've been doing it for years: agreements with councils, community participation and collective self-consumption.

What's still missing

The text of the order, the weight of each criterion, the list of nodes and what exactly a territorial excellence label will be. When it goes out to consultation, I'll read it and report back here.

If the order measures ownership and participation, and not just cheques, it will be a good change for wind power and for the villages that host it.

Frequently asked questions

What is a grid access capacity tender?

A procedure in which Spain's Ministry awards the capacity available at a transmission grid node according to scoring criteria, instead of in order of application. It is regulated by Royal Decree 1183/2020.

When will the wind grid access tenders be called in Spain?

There's no date yet. On 17 November 2026 the Government announced it will put the order regulating them out to public consultation. The tender will come after that.

What will the tenders assess?

According to the announcement: a favourable environmental impact statement, use of the national and European supply chain, and reinvestment in the local municipalities. The weight of each criterion will depend on the text of the order.